হাইড্রোগ্রাফিক তথ্য

Mongla Port was designed for berthing ships having 8.50 m draft. Upto 1980 there was not any siltation problem either in Jetty front or Channel area. But after 1980 siltation started in Jetty front Area. From that time regular maintenance dredging was performed in jetty front area. In the meantime it was seen that siltation has started in Harbour Area (About 13 Km downstream from Port Jetty). Due to this siltation, 03 times capital dredging project has implemented in the year of 1994 - 1995, 2004 - 2005 & 2013-2014. For regular maintenance dredging, Mongla Port Authority have 02 nos 18” dia Cutter Suction Dredger.

 

Currently another capital Dredging project is ongoing which is scheduled to complete at the end of 2014. After completion of this project, ships having draft of 7.50 m will be able to take berth at Mongla Port.

 

Dredging Plan:

  1. Ongoing: To ensure safe movement of coal carrying ships to 2 X 660 MW Maitree Super Thermal Power Project at Rampal, GoB has approved a project titled “Capital Dredging in Pussur Channel from Mongla Port to Rampal Power Plant”. Under this project total 3.88 million cu.m spoil will be dredged by Cutter Suction Dredger and Trailing Suction Hopper Dredger.
  2. Under Approval Process: To achieve sufficient draft of 10.5/11 meter draft vessel (Upto Anchorage Area) a project titled “Dredging at the Outer Bar Area of Pussur Channel” has prepared which is now under process of approval by GoB. In this project total 10.3 million cu.m spoil will be dredged by Trailing Suction Hopper Dredger.

 

Dredging History

 

From the establishment of the Port, the quantity of maintenance dredging by MPA’s own fund is as follows:

 

Dredging period

Dredger Authority

Dredging Area

Dredging Quantity

(Million cu.m)

Total expenditure (Million Taka)

Dredger Type

1979-1981

Water Dev. Board

Jetty front(J5-J9)

0.325

8.96

CSD

1983-1987

BIWTA

Jetty front(J5-J9)

0.695

30.94

CSD

1988-1990

Water Dev. Board

Jetty front(J5-J9) & Confluence

0.523

28.56

CSD

1993-1996

Khanak dredger of Ctg. Port.

(Trailing Suction Hopper Dredger)

Southern Anchorage confluence & Sabur Beacon

0.226

29.89

TSHD

1994-2001

Water Dev. Board

Jetty front (J5-J9)

0.813

97.14

CSD

2003-2004

Water Dev. Board

Jetty  no- 8 & 9

0.069

8.05

CSD

2004-2005

Basic dredging Co.

Jetty  no- 8 & 9

0.054

7.24

CSD

2005-2006

Water Dev. Board

Jetty  no- 8 & 9

0.069

9.05

CSD

2007-2008

Water Dev. Board

Jetty  no- 8 & 9

0.108

19.41

CSD

2009-2010

Water Dev. Board

Jetty  no- 8 & 9

0.071

15.76

CSD

2012-2013

MPA’s own Dredger

Jetty  no- 8 & 9

0.017

-

CSD

2015-2016

AZ dredging Company Ltd

Approach and Pontoon front of Nil Komol

0.155

31.97

CSD

Total

3.125

286.97

 

 

 

 

 

 

In spite of above MPA has carried out 03 Capital Dredging Project under ADP fund which are as follows:

 

Dredging period

Dredging Company

Dredging Area

Dredging Quantity

(Million cu.m)

Total expenditure (Million Taka)

Dredger Type

1991-1992

China Harbour Engineering Company, China

Harbour Area

3.551

308.80

CSD

2000-2004

PT. Rukindo- Basic Dredging Partnership (a joint venture of Indonesia and Bangladesh).

Harbour Area

2.79

454.80

CSD & TSHD

2013-2014

China Harbour Engineering Company, China

Harbour Area

3.406

1118.50

CSD

Total

9.747

1882.1

 